Our Bathroom Project Process

1. Demolition (week 1): We will take 1-2 days to do demolition on your bathroom. This includes removing old cabinets, countertops, shower, tubs or jacuzzi tubs, any necessary walls and soffits, and flooring/baseboards.

2. Rough-ins (week 1): It takes us 1-3 days to do framing, plumbing re-routes, fixture rough-ins, electrical routing, and HVAC work.

3. Drywall (week 1/2): We will take 1-4 days to hang, mud, sand, and texture match (if needed) drywall.

4. Painting (week 2): Painting the bathroom walls and ceiling will take us 1-2 days.

5. Shower pan(week 2): The shower pan and threshold, and any shower benches will be made.

6. Cement board (week 2/3): The shower walls and bathroom flooring (if tile) will have cement board installed. Shower cement board will be fully waterproofed.

7. Tile install (week 3/4): Bathroom floor tile, shower pan tile, and shower wall tile will be installed.

8. Vanity install (week 3/4): The vanity will be installed after floor tile. If the flooring is LVP, vanity will be installed prior to the LVP and then the LVP will be installed. Second payment is collected.

9. Countertops measured and installed (week 4/5): The countertops will be templated and installed about a week later.

10. Fixture connections (week 4/5): Shower and vanity plumbing fixtures will be connected. The tub (if applicable) will be installed and connected as well.

11. Custom shower glass (week 6/7): If applicable, shower glass will be measured as soon possible. It takes about 2 weeks for glass to be fabricated and installed.

12. Punch list for Completion: Your project is not complete until any punch-list items are resolved. Final payment is collected.